Monitor the AP implementation and edge testing.
Site visits to location of project.
Follow up with network services that edge testing is completed and signed off.
Follow up with the cabling group is satisfied with cabling and sign off.
Prepare lesson learned meetings with the team members.
An IT team meeting is scheduled for Friday April 2nd