· An Access Point location was completed by the college NE group.
· Further discussion on where the facilities application equipment will reside in the telecomm room.
· The infrastructure parts have arrived in facilities.
· The project is still on schedule further review of timeline will be discussed on Dec. 17th.
· Site visits.
· Some of the infrastructure has been installed in the telecomm closet.
· College cabling representative have communicated with the bookstore manager on estimated timed when the cabling will be removed and installed.
· Working with infrastructure has to when the AP’s can be installed.
Thursday, December 10, 2009
Thursday, November 19, 2009
progress update
·Sent out first floor layout of building to cabling group.
· The cabling quote has approval from facilities.
· The infrastructure quote has approval from facilities.
· The project is still on schedule.
· Site visits.
· College cabling representative preparing to meet with bookstore client has to when they can remove existing cabling that will least impact the bookstore client.
· The cabling quote has approval from facilities.
· The infrastructure quote has approval from facilities.
· The project is still on schedule.
· Site visits.
· College cabling representative preparing to meet with bookstore client has to when they can remove existing cabling that will least impact the bookstore client.
Wednesday, November 11, 2009
Progress Report
·Sent out first floor layout of building to cabling group.
· Forward the cabling quote to facilities for approval.
· Forward the infrastructure quote to facilities for approval.
· Working with NE group on infrastructure required for the project.
· Meet with IT team, facilities, and client to reviewed timeline of activities.
· Communicating with bookstore on an accurate time to implementing cable through the ceiling in the bookstore.
· Forward the cabling quote to facilities for approval.
· Forward the infrastructure quote to facilities for approval.
· Working with NE group on infrastructure required for the project.
· Meet with IT team, facilities, and client to reviewed timeline of activities.
· Communicating with bookstore on an accurate time to implementing cable through the ceiling in the bookstore.
Thursday, October 29, 2009
Progress Update
Reviewing the design drawings from facilities with the NE, cabling, and telephone group.
Working with the cabling group on quote from contractor.
Requested a quote from the infrastructure vendor.
Working with NE group on infrastructure required for the project.
IT team meeting is scheduled on Nov, 3rd with client and facilities to review the clients decision on design options, estimated timelines, and group activities.
Working with the cabling group on quote from contractor.
Requested a quote from the infrastructure vendor.
Working with NE group on infrastructure required for the project.
IT team meeting is scheduled on Nov, 3rd with client and facilities to review the clients decision on design options, estimated timelines, and group activities.
Tuesday, October 13, 2009
Progress Update
- Completed a walkthrough to review departments relocating and checked on future location site.
- Work with IT project manager to tranfer information on project to new IT PM.
- A meeting is scheduled to review project information from facilities.